In order to complete the repair work the following lane and ramp closures will be in place, 24/7 round the clock, beginning at 7 p.m. on Sunday, Sept. 30 and reopening to all traffic at 6 a.m. on Friday, October 5.
- Eastbound I-70 right lane at the 38th Street Bridge
- Northbound I-635 to eastbound I-70 ramp
- Eastbound I-70 to 38th Street ramp
Drivers should expect major delays during peak commute times and must use alternate routes during the ramp closures.
Updated daily traffic information for this project can be viewed online at: www.ksdot.org/kcmetro/laneclose.asp.
Project work is scheduled to be completed on Friday, October 5, weather permitting.