TRAFFIC ALERT: Central Avenue Bridge over I-70 for Monday-Friday, October 19-23
KANSAS CITY, KAN. ---- Westbound Central Avenue on the bridge over I-70 will be reduced to ONE OPEN LANE, 24/7 round the clock, for repair work beginning at 9 a.m. on Monday, October 19 and will reopen to all traffic at 6 pm on Friday, October 23, weather permitting in Kansas City, KS (Wyandotte County). All adjacent interchange ramps will remain open.
Project work includes expansion joint repairs, deck patching, repair of bridge rail barrier and repair work underneath the bridge deck.
The project contractor, PCI (Minneapolis, MN) will complete repairs on the bridge deck and then suspend the project for the winter season. Then in Spring 2016, the contractor will resume work and complete final repairs underneath the bridge with no planned impacts to traffic.
Traffic will be directed through the project work zone via cones and signage. Drivers should expect some delays and should allow extra time for their daily commutes.
Updated daily traffic information for this bridge repair project and for the entire Kansas City Metro Area can be viewed online at: www.ksdot.org/kcmetro/laneclose.asp.
The Kansas Department of Transportation urges all motorists to be alert, obey the warning signs, and “Give ‘Em a Brake!” when approaching and driving through the project work zone.
Tuesday, June 9, 2015
KANSAS CITY METRO TRAFFIC ALERT: Santa Fe Trail Drive from 101st Street to 105th Street
Kansas Department of Transportation
KANSAS CITY, KAN. ----- Northbound and southbound Santa Fe Trail Drive from 101st Street to 105th Street will be fully to all traffic for the setting of bridge girders, 24/7 round the clock beginning at 7 p.m. on Monday, June 8 and will reopen to all traffic at 6 a.m. on Wednesday, June 10, weather permitting.
Due to equipment issues the bridge girders can’t be unloaded until Tuesday afternoon.
Thus the trucks carrying the bridge girders will remain on the closed portion of Santa Fe Trail Drive and the girders will be installed overnight on Tuesday night. We apologize for the delayed reopening,
Marked detour will be provided (see detour map above). Santa Fe Trail Drive traffic will detour via 99th Street to Lackman Road to 107th Street.
Advance message boards will alert drivers to the full roadway closure. Traffic will be directed via signage, cones and barricades. Drivers should expect delays and must use alternate routes during the overnight roadway closures.
Tuesday, May 12, 2015
KANSAS TRAFFIC ALERT: K-10 from E1650 Road to E1900 Road for Monday, May 11-Late December 2015 in Lawrence
Kansas Department of Transportation
KANSAS CITY, KAN. ---- Eastbound and westbound K-10 from E1650 Road to E1900 Road will continue to be reduced to one lane in each direction, with one change: the eastbound K-10 single lane will be shifted side-by-side into the existing westbound K-10 passing lane.
Both eastbound and westbound K-10 traffic will then be traveling side-by-side on the existing westbound K-10 lanes in this area. This new traffic shift will be in place, 24/7 round the clock, beginning at 8:00 a.m. on Monday, May 11 Tuesday, May 12, weather permitting, through late December 2015 in Lawrence (Douglas County).
Tuesday, May 5, 2015
KANSAS CITY METRO TRAFFIC ALERT: I-70 to I-35 southbound ramp bridge will open June 1
KANSAS CITY, KAN. – Following an extensive repair, the closed I-70 eastbound to I-35 southbound ramp bridge will reopen June 1.
The ramp bridge was temporarily closed April 14 after a routine inspection found significant deterioration to the structure. Initially the closure was to last 2-3 weeks. However, MoDOT determined a more extensive fix was the appropriate action which will require more time.
The deteriorated section of the structure will be replaced. The replacement will include the addition of 1,416 new bolts and adding 7,500 pounds of steel.
By extending the project by several weeks for a more comprehensive repair, crews should not have to return for future repairs to the section.
For more information about other MoDOT projects, please visit MoDOT’s website at www.modot.mo.gov/kansascity. For instant updates, follow MoDOT_KC on Twitter or send questions and comments to kccustomerrelations@modot.mo.gov.
We want your feedback on our work zones! Rate Our Work Zones at www.modot.org/kansascity
The ramp bridge was temporarily closed April 14 after a routine inspection found significant deterioration to the structure. Initially the closure was to last 2-3 weeks. However, MoDOT determined a more extensive fix was the appropriate action which will require more time.
The deteriorated section of the structure will be replaced. The replacement will include the addition of 1,416 new bolts and adding 7,500 pounds of steel.
By extending the project by several weeks for a more comprehensive repair, crews should not have to return for future repairs to the section.
For more information about other MoDOT projects, please visit MoDOT’s website at www.modot.mo.gov/kansascity. For instant updates, follow MoDOT_KC on Twitter or send questions and comments to kccustomerrelations@modot.mo.gov.